TxDOT Research Project

Determine Proper Selection of Ride Quality Pay Adjustment Schedule and Re-Evaluation of Current Bonus/Penalty Structure

What Was the Need?
TxDOT lets approximately 300 projects annually that include paving related work. Most of these projects include the ride quality specification as outlined in Standard Specification Item 585, Ride Quality for Pavement Surfaces. While inclusion of Item 585 occurs throughout the state, the selection of pay schedule and enforcement of the specification varies widely within TxDOT. In addition, the bonus/penalty structure within Item 585 was developed over 13 years ago.

What's the Solution?
Objectives for this project [1.] Conduct a synthesis of ride quality selection and enforcement. [2.] Determine an estimate of the amount of ride quality bonus paid by TxDOT annually. [3.] Perform an analysis on various paving projects to investigate ride quality improvement. [4.] Establish a decision framework to assist districts in selecting and enforcing the most appropriate ride quality pay schedule. [5.] Evaluate modifications to the bonus/penalty structure within the specification. [6.] Investigate whether or not adjustments can be made to the bonus/penalty structure to tighten the specification in a way that smoother pavements will be achieved throughout the state. [7.] Investigate establishing separate bonus/penalty structures for flexible pavements and rigid pavements.

Project Number
0-6986
Status
Completed

link icon Copy link to this project.

Start Date
9/1/2018
End Date
8/31/2020
Performing Institution(s)
Texas A & M Transportation Institute (TTI)
Research Team
RS: Charles Gurganus
Sponsor
Project Manager
Joanne Steele
Contract Specialist
Patti Dathe
TxDOT Advisor
Andy Naranjo, MTD
Enad Mahmoud, MTD
Miles Garrison, MTD
Travis Patton, MTD
Ben Engelhardt, AUS
Ruben Carrasco, AUS
James Robbins, BRY
Jesus Noriega, PHR
Amount Funded
FY19: $101,748
FY20: $100,422
Source
RFP 19-137 Determine Proper Selection of Ride Quality Pay Adjustment Schedule and Re-evaluation of Current Bonus/Penalty Structure
Page:
Functional Area
Construction, Maintenance and Materials
Index Terms
Construction projects
Contract administration
Deicison making
Incentives
Penalties
Ride quality
Specifications
Lead University
TTI
Researcher
Gurganus, Charles F.
TxDOT District
MTD
AUS
BRY
PHR

Registered users may add comments. Comments will be shown with usernames.

Comments
Record Added:
11/7/2018
Record Updated:
7/22/2023 5:36 AM EDT

Report a broken link or error ».

Made possible by the generous support of the
Texas Department of Transportation Research and Technology Implementation Division (RTI)


Center for Transportation Research | Cockrell School of Engineering | The University of Texas at Austin

©2024 Center for Transportation Research | Web Accessibility Policy | Web Privacy Policy